Planning support for the conversion of the ColdEnd at Novelis Deutschland GmbH

Overview

Location: Nachterstedt/Seeland, Germany
Project duration: 12 months


HÖRMANN Rawema Engineering & Consulting GmbH successfully implemented the planning support for the conversion of the ColdEnd. The aim was to precisely design piping and steelwork layouts, to technically clarify measurement systems including explosion protection and to support the implementation by coordinating suppliers and construction sites on schedule.

 

Project content

3D layout planning for pipe routing and steelwork

Development of the three-dimensional (3D) layout planning for pipe routing and steelwork. Clear routes, media paths and construction points for collision-free integration.

As-built survey using 3D laser scanning

Recording of existing pipes using 3D laser scanning. Precise geometric data as a basis for planning, comparison and variant evaluation.

Technical clarification of the piping concept

Development and clarification of the technical requirements of the piping system. Ensuring functionality and interface compatibility.

Measurement systems and sensors including explosion protection

Support with the technical development of the necessary measurement systems and measurement sensors including explosion protection. Specifications for measuring points and their positioning.

2D layout planning of the piping system

Two-dimensional (2D) layout planning of the piping system including cyclone installation areas and positioning of the measuring points. Transparent representation of path relationships and connections.

Supplier management

Creation of requirement specifications and specifications as well as coordination of suppliers. Clarified interfaces and documented requirements for smooth implementation.

Construction site organization during implementation

Organization of the construction site during the implementation phase. Structured processes and clear responsibilities on site.


Advantages of our solution

  • Collision-free: 2D/3D layouts and 3D laser scanning ensure consistent planning and avoid paving conflicts.
  • Interface safety: Technical clarification of the piping concept and coordinated measuring systems reduce risks at media and construction interfaces.
  • Explosion protection: Consideration of safety requirements increases operational safety and facilitates approvals.
  • On-time implementation: Supplier management and construction site organization stabilize milestones and reduce rework.
  • Transparency: Requirement specifications and specifications create a clear basis for decision-making and implementation.
     

Contact us

Interested in a customized factory planning solution for your company?
Contact our experienced team at HÖRMANN Rawema for a no-obligation consultation. >>

hoermann-rawema-refernz-Novelis-Germany-GmbH-1
hoermann-rawema-refernz-Novelis-Germany-GmbH-2